
Ramp Impacts
I-80 Ramps
Eastbound I-80 Off-Ramp to 2300 East Closure
Crews will close the eastbound I-80 off-ramp to 2300 East overnight on Wednesday, Sept. 13, from 10 p.m. to 5 a.m. while crews work on the ramp.
During this closure, drivers can exit eastbound I-80 from the off-ramp at 1300 East.
.png)
Westbound I-80 On-Ramp from 1300 East Closure
Crews will close the westbound I-80 on-ramp from 1300 East overnight on Wednesday, Sept. 13, from 10 p.m. to 5 a.m. while crews work on the ramp.
​
During this closure, drivers can access westbound I-80 from the on-ramp at 700 East.
.png)
Ramp Reconstruction
The following ramps are currently being reconstructed as part of the project:
-
Eastbound I-80 on-ramp from 1300 East
-
Westbound I-80 on-ramp from northbound 1300 East
-
Westbound I-80 off-ramp to 1300 East
​
To reconstruct each ramp, crews will shift traffic to a temporary lane. Then, crews will remove and crush the concrete pavement that is on the existing ramp and replace it with new concrete.
Drivers can expect intermittent closures of these ramps through 2023 while they are being reconstructed. They should also expect uneven pavement and drainage grates on these ramps.
Plan ahead and check UDOT Traffic before traveling.
In 2022, crews reconstructed two ramps on I-80:
-
Eastbound I-80 off-ramp to 2300 East
-
Westbound I-80 on-ramp from 2300 East


The construction schedule and activities are weather-dependent and subject to change.
I-215 Ramps
Northbound I-215 On-Ramp from 3300 South
Crews will reduce the northbound I-215 on-ramp from 3300 South in Millcreek to one lane as early as Monday, July 17, and continuing through July 2023. This will allow crews to complete drainage work.
Drivers should plan ahead and expect minor delays.

Ramp Reconstruction
The following ramps are currently being reconstructed as part of the project:​
-
Northbound I-215 on-ramp from 3800 South
-
Northbound I-215 off-ramp to 3300 South and 3900 South
-
Southbound I-215 on-ramp from 3300 South
​
To reconstruct each ramp, crews will shift traffic to a temporary lane. Then, crews will remove and crush the concrete pavement that is on the existing ramp and replace it with new concrete.
During reconstruction, drivers can expect intermittent closures of these ramps through 2023 as well as uneven pavement and drainage grates on these ramps.
Plan ahead and check UDOT Traffic before traveling.
In 2022, crews reconstructed three ramps on I-215:
-
Southbound I-215 on-ramp from 3900 South
-
Southbound I-215 off-ramp to 3900 South
-
Southbound I-215 off-ramp to 4500 South


The construction schedule and activities are weather-dependent and subject to change.