Ramp Impacts

Ramp Shoulder Closures

Crews are beginning to reconstruct the following ramps in Millcreek:

  • Southbound I-215 on-ramp from 3300 South

  • Southbound I-215 off-ramp to 3900 South

  • Southbound I-215 on-ramp from 3900 South

  • Southbound I-215 off-ramp to 4500 South

As part of this work, crews will close the shoulders of the ramps to prepare for temporary paving. The shoulders will be closed during daytime and nighttime hours through early August. Following this work, temporary paving will occur.

The construction schedule and activities are subject to change.

​​

Ramp Reconstruction

The northbound I-215 off-ramp to 3900 South and 3300 South, and the on-ramp from northbound 1300 East to westbound I-80, are being reconstructed. Work on these ramps began in mid-June. Crews have since removed and crushed the existing concrete pavement on the ramps.

To complete reconstruction, crews will place new concrete pavement on the ramps. This work is scheduled to take place in late summer 2021.  

 

 These activities will increase noise and vibration for nearby properties. Additional impacts include:

  • Shifted traffic

  • Increased dust

  • Overnight lighting

​​

15688_MAP_I-215 Ramp Map_Shoulder Closures July 28-01 (1).jpg
15688_MAP_I-80-Ramp-Map_online.jpg
15688_MAP_I-215-Ramp-Map_online.jpg